Heena Presidency
72/2, 73/1,2,3,4, 74/1,2, 75/1, 79/1,3,4, Mira Road, 401107
- Litigation pending (1). MahaRERA's litigation disclosure lists 1 pending case against this project.
- Possession delayed ~2 yrs. Originally promised Dec 2024, now proposed Dec 2026 per the RERA filing.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Where it is · 72/2, 73/1,2,3,4, 74/1,2, 75/1, 79/1,3,4, Mira Road
Area guide
What it's like to buy in Mira Road
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
The city's northern value frontier, densifying fast.
- Growth drivers:
- Metro 9 extension, spillover from Borivali pricing.
- Who buys here:
- First-time buyers stretching for a 1–2 BHK.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Architect
Design profile
Browse other projects associated with this architect to compare design and delivery patterns.
No other projects are linked to this architect yet.
Official RERA facts
- Registration
- P51800001920
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2026originally December 2024
- Construction
- 97.3% complete
- Units sold
- 137 of 143
Similar projects in Mira Road
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Mira Road compares.
In Mira Road
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.