High risk
  • Possession delayed ~3 yrs. Originally promised Dec 2019, now proposed Mar 2023 per the RERA filing.
  • Possession date passed. The proposed possession date (Mar 2023) has passed with construction at 90.9%.
Satellite view of this address

Where it is · 11 AND 15, PALGHAR EAST

Promoter

Builder profile

Builder
SHILPA DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P99000010104
Status
Ongoing
Stage
Certificate Signed
Possession
March 2023originally December 2019
Construction
90.9% complete
Units sold
0 of 0

Similar projects in PALGHAR EAST

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how PALGHAR EAST compares.

Data sourced from the official MahaRERA portal; complaints last synced 7 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.