Hetali Vishnu Bhavan
91A, 91/1 to 91/4, Akurli, Kandivali East, 400101
- Litigation pending (3). MahaRERA's litigation disclosure lists 3 pending cases against this project.
- Possession date passed. The proposed possession date (Dec 2025) has passed with construction at 63%.
- Promised amenities not started. Gymnasium, Clubhouse are at 0% build with possession due Dec 2025 per the RERA filing.
Where it is · 91A, 91/1 to 91/4, Akurli, Kandivali East
Area guide
What it's like to buy in Akurli
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Retail-and-BPO hub with dense mid-income housing on both sides.
- Growth drivers:
- Mindspace offices, Link Road retail, Metro 2A.
- Who buys here:
- Mid-income families, first-time buyers.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51800034561
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2025
- Construction
- 63% complete
- Units sold
- 0 of 0
Keep exploring
Where this project sits, who built it, and how Akurli, Kandivali East compares.
In Akurli, Kandivali East
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.