HILL VIEW RESIDENCY PHASE I PROJECT II BUILDING A AND B
by KUMAR BEHARAY PROPERTIES LLP
S NO 69 5B 2, 69 8 1, AND 70 1 TO 17A1, BEHIND MAHATMA SOCIETY KOTHRUD, 411038
- Litigation pending (3). MahaRERA's litigation disclosure lists 3 pending cases against this project.
- Possession date passed. The proposed possession date (Dec 2022) has passed with construction at 90.9%.
- Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2022 per the RERA filing.
Where it is · S NO 69 5B 2, 69 8 1, AND 70 1 TO 17A1, BEHIND MAHATMA SOCIETY KOTHRUD
Area guide
What it's like to buy in BEHIND MAHATMA SOCIETY KOTHRUD
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52100014848
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2022
- Construction
- 90.9% complete
- Units sold
- 0 of 0
Keep exploring
Where this project sits, who built it, and how BEHIND MAHATMA SOCIETY KOTHRUD compares.
In BEHIND MAHATMA SOCIETY KOTHRUD
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.