Under construction

Hillcrest Appartments

MahaRERA P51700012086High risk

by aasanghar construction

1551A,1581,1592B,1592C,1592D,1593B,1593C, Titwala, 421605

Official record
Dec 2026
Possession
65.9%
Built
52
Complaints
0
Units
High risk
  • Possession delayed ~9 yrs. Originally promised Mar 2018, now proposed Dec 2026 per the RERA filing.
  • 52 RERA complaints. 52 complaint records are disclosed against this project on MahaRERA.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Satellite view of this address

Where it is · 1551A,1581,1592B,1592C,1592D,1593B,1593C, Titwala

Promoter

Builder profile

Builder
aasanghar construction

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P51700012086
Status
Ongoing
Stage
Certificate Signed
Possession
December 2026originally March 2018
Construction
65.9% complete
Units sold
0 of 0

Similar projects in Titwala

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Titwala compares.

Data sourced from the official MahaRERA portal; complaints last synced 17 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.