HIMBINDU
292 PT, 292/21 TO 30, Goregaon West, 400104
- Litigation pending (1). MahaRERA's litigation disclosure lists 1 pending case against this project.
- 1 appeal at MahaREAT. 1 complaint against this project has been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
- Possession delayed ~3 yrs. Originally promised Dec 2018, now proposed May 2022 per the RERA filing.
- Possession date passed. The proposed possession date (May 2022) has passed with construction at 52.7%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due May 2022 per the RERA filing.
Where it is · 292 PT, 292/21 TO 30, Goregaon West
Area guide
What it's like to buy in Goregaon West
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Film City flank with large integrated townships on both flanks.
- Growth drivers:
- Oberoi/NESCO belt, Metro 7, Western Express Highway offices.
- Who buys here:
- Upgraders wanting township amenities without Powai prices.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51800003502
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- May 2022originally December 2018
- Construction
- 52.7% complete
- Units sold
- 0 of 0
Similar projects in Goregaon West
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Goregaon West compares.
In Goregaon West
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.