Under construction

HOLIDAY MAIYAAN KARJAT

MahaRERA P52000000477High risk

by B QUBES

SURVEY NUMBER 185/1, 185/2, 185/3, 185/4, 185/5, 185/6, Karjat, 410201

Official record
Apr 2026
Possession
72.7%
Built
0
Complaints
132
Units
High risk
  • Litigation pending (1). MahaRERA's litigation disclosure lists 1 pending case against this project.
  • Possession delayed ~7 yrs. Originally promised Apr 2019, now proposed Apr 2026 per the RERA filing.
  • Possession date passed. The proposed possession date (Apr 2026) has passed with construction at 72.7%.
Satellite view of this address

Where it is · SURVEY NUMBER 185/1, 185/2, 185/3, 185/4, 185/5, 185/6, Karjat

Area guide

What it's like to buy in Karjat

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
B QUBES

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
Trupti Panchal

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P52000000477
Status
Ongoing
Stage
Certificate Signed
Possession
April 2026originally April 2019
Construction
72.7% complete
Units sold
131 of 132

Similar projects in Karjat

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Karjat compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.