Under construction

Hrishita Apartment

MahaRERA P51600011155High risk

by Hrishita Buildcon & Infrastructures Pvt. Ltd

Survey No.73/2-A,Plot No.4, C. T. S No.2435, Chunchale, Shiwar, Nashik, SHIVAR, 422010

Official record
Jun 2022
Possession
23.5%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~4 yrs. Originally promised Aug 2018, now proposed Jun 2022 per the RERA filing.
  • Possession date passed. The proposed possession date (Jun 2022) has passed with construction at 23.5%.
Satellite view of this address

Where it is · Survey No.73/2-A,Plot No.4, C. T. S No.2435, Chunchale, Shiwar, Nashik, SHIVAR

Promoter

Builder profile

Builder
Hrishita Buildcon & Infrastructures Pvt. Ltd

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51600011155
Status
Ongoing
Stage
Certificate Signed
Possession
June 2022originally August 2018
Construction
23.5% complete
Units sold
0 of 0

Similar projects in SHIVAR

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how SHIVAR compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.