IDEAL AVENUE BUILDING NO 3 TYPE B1D WING B
by SHREE SAI SAMARTH BUILDERS AND DEVELOPERS
SURVEY NO 179, 180, 181, UMROLI, 401404
- Possession delayed ~4 yrs. Originally promised Dec 2022, now proposed Apr 2027 per the RERA filing.
- Behind schedule. Possession is due Apr 2027 but construction is only at 39.5%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Apr 2027 per the RERA filing.
Where it is · SURVEY NO 179, 180, 181, UMROLI
Area guide
What it's like to buy in UMROLI
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Architect
Design profile
Browse other projects associated with this architect to compare design and delivery patterns.
Official RERA facts
- Registration
- P99000009483
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- April 2027originally December 2022
- Construction
- 39.5% complete
- Units sold
- 15 of 37
Similar projects in UMROLI
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how UMROLI compares.
In UMROLI
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.