High risk
  • Possession delayed ~3 yrs. Originally promised Sept 2024, now proposed Apr 2027 per the RERA filing.
  • Behind schedule. Possession is due Apr 2027 but construction is only at 41.8%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Apr 2027 per the RERA filing.
Satellite view of this address

Where it is · 232A2, MAUJE UMROLI

Promoter

Builder profile

Builder
T. L. REALITIES

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
RAJESHYSATGHARE SATGHARE

Browse other projects associated with this architect to compare design and delivery patterns.

No other projects are linked to this architect yet.

Official RERA facts

Registration
P99000027773
Status
New
Stage
Certificate Signed
Possession
April 2027originally September 2024
Construction
41.8% complete
Units sold
0 of 0