High risk
  • Possession delayed ~1 yr. Originally promised Dec 2025, now proposed Apr 2027 per the RERA filing.
  • Promised amenities not started. Clubhouse is at 0% build with possession due Apr 2027 per the RERA filing.
Satellite view of this address

Where it is · Survey No -31, Hissa no - 2/3, Rasayani

Promoter

Builder profile

Builder
DYNAMIC ENTERPRISES

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
Destination Architecture Interior Designs

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P52000021766
Status
New
Stage
Certificate Signed
Possession
April 2027originally December 2025
Construction
81.8% complete
Units sold
119 of 174

Similar projects in Rasayani

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Rasayani compares.

Data sourced from the official MahaRERA portal; complaints last synced 24 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.