Jun 2022
Possession
28.2%
Built
0
Complaints
0
Units
High risk
  • Litigation pending (2). MahaRERA's litigation disclosure lists 2 pending cases against this project.
  • Possession date passed. The proposed possession date (Jun 2022) has passed with construction at 28.2%.
Satellite view of this address

Where it is · 39 1 1 , 39 1 3 TO 39 1 8 , 39 1 10 TO 39 1 12 , 39 1 2 1 TO 39 1 2 4, NIBM

Promoter

Builder profile

Builder
AGCONSTRUCTIONS

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52100019566
Status
New
Stage
Certificate Signed
Possession
June 2022
Construction
28.2% complete
Units sold
0 of 0

Similar projects in NIBM

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how NIBM compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.