INDUSTRIAL BUILDING NO 1
by SHREE NARAYAN INDUSTRIAL DEVELOPERS
S NO 46 H .NO 2/1,2/2,2/4,2/11, S.NO 47 H .NO 4/5, Vasai-Virar City (M Corp), 401208
- Possession delayed ~2 yrs. Originally promised Dec 2021, now proposed Dec 2023 per the RERA filing.
- Possession date passed. The proposed possession date (Dec 2023) has passed with construction at 57.1%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2023 per the RERA filing.
Where it is · S NO 46 H .NO 2/1,2/2,2/4,2/11, S.NO 47 H .NO 4/5, Vasai-Virar City (M Corp)
Area guide
What it's like to buy in Vasai-Virar City (M Corp)
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P99000011126
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2023originally December 2021
- Construction
- 57.1% complete
- Units sold
- 0 of 0
Similar projects in Vasai-Virar City (M Corp)
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Vasai-Virar City (M Corp) compares.
In Vasai-Virar City (M Corp)
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.