IPSIT NAVODAY PHASE 5
GUT NO 995/1, Palghar, 401404
- Possession delayed ~5 yrs. Originally promised Mar 2019, now proposed Jun 2024 per the RERA filing.
- Possession date passed. The proposed possession date (Jun 2024) has passed with construction at 60.5%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2024 per the RERA filing.
Where it is · GUT NO 995/1, Palghar
Area guide
What it's like to buy in Palghar
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Architect
Design profile
Browse other projects associated with this architect to compare design and delivery patterns.
Official RERA facts
- Registration
- P99000003777
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- June 2024originally March 2019
- Construction
- 60.5% complete
- Units sold
- 86 of 99
Similar projects in Palghar
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Palghar compares.
In Palghar
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.