ISHWAR BLOSSOM
PLOT NO. 88, CTS NO. 3786 AT SURYODAYA CO-OP SOC., KANSAI SECTION, 421501
- Possession delayed ~1 yr. Originally promised Dec 2024, now proposed Jun 2026 per the RERA filing.
- Possession date passed. The proposed possession date (Jun 2026) has passed with construction at 72.3%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2026 per the RERA filing.
Where it is · PLOT NO. 88, CTS NO. 3786 AT SURYODAYA CO-OP SOC., KANSAI SECTION
Area guide
What it's like to buy in KANSAI SECTION
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
The value frontier beyond Kalyan — low-rise affordability, improving rail links.
- Growth drivers:
- Extended suburban rail, industrial-belt employment, lowest entry prices in MMR.
- Who buys here:
- First-home buyers stretching every rupee.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Architect
Design profile
Browse other projects associated with this architect to compare design and delivery patterns.
Official RERA facts
- Registration
- P51700049361
- Status
- New
- Stage
- Certificate Signed
- Possession
- June 2026originally December 2024
- Construction
- 72.3% complete
- Units sold
- 4 of 23
Similar projects in KANSAI SECTION
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how KANSAI SECTION compares.
In KANSAI SECTION
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 21 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.