- Promised amenities not started. Landscaped Garden is at 0% build with possession due Apr 2027 per the RERA filing.
Area guide
What it's like to buy in VILLAGE ADAI
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Architect
Design profile
Browse other projects associated with this architect to compare design and delivery patterns.
No other projects are linked to this architect yet.
Official RERA facts
- Registration
- P52000046774
- Status
- New
- Stage
- Certificate Signed
- Possession
- April 2027originally December 2026
- Construction
- 81.8% complete
- Units sold
- 20 of 63
Keep exploring
Where this project sits, who built it, and how VILLAGE ADAI compares.
In VILLAGE ADAI
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 18 Sept 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.