High risk
  • Possession delayed ~2 yrs. Originally promised Nov 2023, now proposed Nov 2025 per the RERA filing.
  • Possession date passed. The proposed possession date (Nov 2025) has passed with construction at 68.3%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Nov 2025 per the RERA filing.

Promoter

Builder profile

Builder
NILESH MADHUKAR JADHAV

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51600025514
Status
New
Stage
Certificate Signed
Possession
November 2025originally November 2023
Construction
68.3% complete
Units sold
0 of 0

Similar projects in CHUNCHALE

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how CHUNCHALE compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.