Under construction

JAI SHREERAM PRASANNA CHSL

MahaRERA P51800011427High risk

by RIYAZ RAMZAN SHAH

CTS 939, 939 / 1 TO 4, Kurla, 400070

Official record
Aug 2026
Possession
72.6%
Built
1
Complaints
26
Units
High risk
  • Possession delayed ~4 yrs. Originally promised Jun 2022, now proposed Aug 2026 per the RERA filing.
  • Possession date passed. The proposed possession date (Aug 2026) has passed with construction at 72.6%.
Satellite view of this address

Where it is · CTS 939, 939 / 1 TO 4, Kurla

Area guide

What it's like to buy in Kurla

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Kurla / ChemburMid-income

Central crossroads reborn via freeway and Metro links.

Growth drivers:
Eastern Freeway, Monorail/Metro, BKC proximity at half the price.
Who buys here:
BKC-bound professionals and long-time Chembur families.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
RIYAZ RAMZAN SHAH

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
Allied Associates

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P51800011427
Status
Ongoing
Stage
Certificate Signed
Possession
August 2026originally June 2022
Construction
72.6% complete
Units sold
17 of 26

Similar projects in Kurla

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Kurla compares.

Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.