Under construction
JAY GANESH CONSTRUCTIONS
MahaRERA P52100008689High risk
SR NO.33/3, Baner, 411045
Post your property hereOwn or renting out a unit in JAY GANESH CONSTRUCTIONS? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Baner come to you.
Dec 2017
Possession
81.8%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Dec 2017) has passed with construction at 81.8%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2017 per the RERA filing.
Satellite view of this address
Where it is · SR NO.33/3, Baner
Area guide
What it's like to buy in Baner
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
JAY GANESH CONSTRUCTION
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52100008689
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2017
- Construction
- 81.8% complete
- Units sold
- 0 of 0
Similar projects in Baner
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
The Balmoral Hillside - Commercial
BanerPoss. June 2029
Rahul Altimus
BanerPoss. October 2026
Achalare Business Capital
BanerPoss. June 2030
SR HOUSE
BanerPoss. May 2031
Stalwart Business Enclave
BanerPoss. December 2028
BotanIQ
BanerPoss. December 2030
Ambrosia Studio
BanerPoss. March 2028
Lumina Towers
BanerPoss. June 2029
Keep exploring
Where this project sits, who built it, and how Baner compares.
In Baner
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.