Official record
Jul 2022
Possession
90.9%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Jul 2022) has passed with construction at 90.9%.
Satellite view of this address

Where it is · 20 to 25 S NO 906/3/2 - 906/4/5, Pathardi Phata

Promoter

Builder profile

Builder
Shivam Developers

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P51600022203
Status
New
Stage
Certificate Signed
Possession
July 2022
Construction
90.9% complete
Units sold
0 of 0

Similar projects in Pathardi Phata

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Pathardi Phata compares.

Data sourced from the official MahaRERA portal; complaints last synced 7 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.