Under construction

K K SOLITAIRE

MahaRERA P51800012460High risk

by Navin M Mehta

278 OF TPS III, CTS NUMBER 5704, Kurla, 400075

Official record
Jan 2021
Possession
90.9%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Jul 2019, now proposed Jan 2021 per the RERA filing.
  • Possession date passed. The proposed possession date (Jan 2021) has passed with construction at 90.9%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jan 2021 per the RERA filing.
Satellite view of this address

Where it is · 278 OF TPS III, CTS NUMBER 5704, Kurla

Area guide

What it's like to buy in Kurla

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Ghatkopar / VikhroliUpper-mid

Metro-1 anchor with Godrej's Vikhroli land bank next door.

Growth drivers:
Metro 1 interchange, Eastern Express Highway, corporate campuses.
Who buys here:
Families wanting east-side connectivity to BKC/Fort.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
Navin M Mehta

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P51800012460
Status
Ongoing
Stage
Certificate Signed
Possession
January 2021originally July 2019
Construction
90.9% complete
Units sold
0 of 0

Similar projects in Kurla

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.