Under construction

K K SUNDARBAN BUILDING H

MahaRERA P52100004320High risk

by K K DEVELOPERS

91/1/A AND 91/1/B, Girim, 413801

Official record
Apr 2027
Possession
69.5%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~8 yrs. Originally promised Dec 2018, now proposed Apr 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Apr 2027 per the RERA filing.
Satellite view of this address

Where it is · 91/1/A AND 91/1/B, Girim

Promoter

Builder profile

Builder
K K DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100004320
Status
Ongoing
Stage
Certificate Signed
Possession
April 2027originally December 2018
Construction
69.5% complete
Units sold
0 of 0