Under construction

K M RESIDENCY

MahaRERA P99000007750High risk

by KM REALITY

33-1 TO 33-19 75/2 27/1APT 27/1BPT27/1CPT 27/1/APT 27/3 27/5A 27/5A 27/5B 27/6 27/7 32/34, Palghar, 401501

Official record
Dec 2027
Possession
77.3%
Built
0
Complaints
90
Units
High risk
  • Possession delayed ~7 yrs. Originally promised Jun 2021, now proposed Dec 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2027 per the RERA filing.
Satellite view of this address

Where it is · 33-1 TO 33-19 75/2 27/1APT 27/1BPT27/1CPT 27/1/APT 27/3 27/5A 27/5A 27/5B 27/6 27/7 32/34, Palghar

Area guide

What it's like to buy in Palghar

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
KM REALITY

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P99000007750
Status
Ongoing
Stage
Certificate Signed
Possession
December 2027originally June 2021
Construction
77.3% complete
Units sold
80 of 90

Similar projects in Palghar

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Palghar compares.

Data sourced from the official MahaRERA portal; complaints last synced 4 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.