Kalpataru Bliss Apartments
CTS No 4958D pt, 4958D-52Pt, 53Pt, 54Pt, 55 to 71, 75 pt, 76 to 124 of Village Kolekalyan, Andheri, 400098
- Litigation pending (5). MahaRERA's litigation disclosure lists 5 pending cases against this project.
- 1 appeal at MahaREAT. 1 complaint against this project has been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
- Possession date passed. The proposed possession date (Sept 2025) has passed with construction at 81.5%.
Where it is · CTS No 4958D pt, 4958D-52Pt, 53Pt, 54Pt, 55 to 71, 75 pt, 76 to 124 of Village Kolekalyan, Andheri
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Architect
Design profile
Browse other projects associated with this architect to compare design and delivery patterns.
No other projects are linked to this architect yet.
Official RERA facts
- Registration
- P51800020262
- Status
- New
- Stage
- Certificate Signed
- Possession
- September 2025
- Construction
- 81.5% complete
- Units sold
- 76 of 80
Similar projects in Andheri
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Andheri compares.
In Andheri
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 21 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.