High risk
  • Litigation pending (13). MahaRERA's litigation disclosure lists 13 pending cases against this project.
  • Possession delayed ~7 yrs. Originally promised Jun 2021, now proposed Dec 2027 per the RERA filing.
Satellite view of this address

Where it is · 471/A pt, KANDIVALI

Area guide

What it's like to buy in KANDIVALI

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

MaladMid-income

Retail-and-BPO hub with dense mid-income housing on both sides.

Growth drivers:
Mindspace offices, Link Road retail, Metro 2A.
Who buys here:
Mid-income families, first-time buyers.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
Raj Arcades Homes Pvt Ltd

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P51800008716
Status
Ongoing
Stage
Certificate Signed
Possession
December 2027originally June 2021
Construction
90.9% complete
Units sold
359 of 359

Similar projects in KANDIVALI

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how KANDIVALI compares.

Data sourced from the official MahaRERA portal; complaints last synced 20 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.