Under construction
KAMALA APARTMENT
MahaRERA P99000023527Caution
Survey No-58/2B2 Plot No-16 and 17, Palghar East, 401404
Post your property hereOwn or renting out a unit in KAMALA APARTMENT? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Palghar East come to you.
Sept 2022
Possession
90.9%
Built
0
Complaints
0
Units
Caution
- Possession date passed. The proposed possession date (Sept 2022) has passed with construction at 90.9%.
Area guide
What it's like to buy in Palghar East
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
Soham Enterprises
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P99000023527
- Status
- New
- Stage
- Certificate Signed
- Possession
- September 2022
- Construction
- 90.9% complete
- Units sold
- 0 of 0
Similar projects in Palghar East
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Osian Royale
Palghar EastPoss. March 2030
Aadinath Complex Bldg No 1 and 2
Palghar East90.9% builtPoss. December 2018
Madhav Vatika-II
Palghar East90.9% builtPoss. January 2021
Madhav Vatika-III
Palghar East90.9% builtPoss. December 2021
Madhav Vatika - IV
Palghar East90.9% builtPoss. October 2022
Aadinath Complex
Palghar East90.9% builtPoss. September 2020
MADHAV VATIKA - V
Palghar East90.9% builtPoss. December 2024
Vakratund Heights
Palghar East90.5% builtPoss. December 2022
Keep exploring
Where this project sits, who built it, and how Palghar East compares.
In Palghar East
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.