KANAKIA BEVERLY HEIGHTS

MahaRERA P51700051409Caution

by PERIWINKLE CONSTRUCTIONS PRIVATE LIMITED

OLD SURVEY NO 237 NEW SURVEY NO 186 HISSA NO 2, 4, 11, 12 AND 13, Thane, 401105

Official record
Apr 2028
Possession
45.7%
Built
0
Complaints
0
Units
Caution
  • Promised amenities not started. Clubhouse is at 0% build with possession due Apr 2028 per the RERA filing.
Satellite view of this address

Where it is · OLD SURVEY NO 237 NEW SURVEY NO 186 HISSA NO 2, 4, 11, 12 AND 13, Thane

Promoter

Builder profile

Builder
PERIWINKLE CONSTRUCTIONS PRIVATE LIMITED

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P51700051409
Status
New
Stage
Certificate Signed
Possession
April 2028originally December 2027
Construction
45.7% complete
Units sold
0 of 0

Similar projects in Thane

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Thane compares.

Data sourced from the official MahaRERA portal; complaints last synced 7 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.