Clean record
No delays, complaints or enforcement actions in the official disclosures we track.
Area guide
What it's like to buy in VADGHAR
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
PRIME REALTIES
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52000017769
- Status
- New
- Stage
- Certificate Signed
- Possession
- February 2021
- Construction
- 100% complete
- Units sold
- 0 of 0
Similar projects in VADGHAR
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
NEERA HOMES
VADGHAR90.9% builtPoss. August 2022
BHAVESHWAR CAASA
VADGHAR90.9% builtPoss. December 2025
APEX ONE
VADGHAR81.8% builtPoss. June 2024
APEX AARAMBH
VADGHAR81.8% builtPoss. December 2023
SIDDHIVINAYAK EKDANT
VADGHAR73.9% builtPoss. March 2027
SAI KIRAN
VADGHAR62.7% builtPoss. April 2024
ANANT SRUSHTI RESIDENCY
VADGHAR0% builtPoss. August 2023
Keep exploring
Where this project sits, who built it, and how VADGHAR compares.
In VADGHAR
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.