KANTHARIA LAKESIDE
3339/A, Vasai, 401201
- Possession delayed ~2 yrs. Originally promised Dec 2022, now proposed Dec 2024 per the RERA filing.
- Possession date passed. The proposed possession date (Dec 2024) has passed with construction at 81.8%.
- Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2024 per the RERA filing.
Where it is · 3339/A, Vasai
Area guide
What it's like to buy in Vasai
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
The western line's volume market — dense affordable towers past Mira Road.
- Growth drivers:
- Suburban rail quadrupling, coastal-road extensions, MMR's biggest affordable pipeline.
- Who buys here:
- Budget-first buyers who commute the western line.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P99000020016
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2024originally December 2022
- Construction
- 81.8% complete
- Units sold
- 0 of 0
Similar projects in Vasai
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Vasai compares.
In Vasai
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.