High risk
  • Possession delayed ~2 yrs. Originally promised Dec 2022, now proposed Dec 2024 per the RERA filing.
  • Possession date passed. The proposed possession date (Dec 2024) has passed with construction at 81.8%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2024 per the RERA filing.
Satellite view of this address

Where it is · 3339/A, Vasai

Area guide

What it's like to buy in Vasai

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Vasai–VirarValue

The western line's volume market — dense affordable towers past Mira Road.

Growth drivers:
Suburban rail quadrupling, coastal-road extensions, MMR's biggest affordable pipeline.
Who buys here:
Budget-first buyers who commute the western line.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
PROACTIVE HOUSING LLP

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P99000020016
Status
New
Stage
Certificate Signed
Possession
December 2024originally December 2022
Construction
81.8% complete
Units sold
0 of 0

Similar projects in Vasai

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Vasai compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.