Under construction

Kashish Park Ghatkopar

MahaRERA P51800002692High risk

by Ladam Homes Pvt Ltd.

184C pt/ CTS no. 231, Kurla, 400075

Official record
Dec 2022
Possession
90.8%
Built
11
Complaints
0
Units
High risk
  • Litigation pending (1). MahaRERA's litigation disclosure lists 1 pending case against this project.
  • 9 appeals at MahaREAT. 9 complaints against this project have been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
  • Possession delayed ~2 yrs. Originally promised Jun 2021, now proposed Dec 2022 per the RERA filing.
  • 11 RERA complaints. 11 complaint records are disclosed against this project on MahaRERA.
  • Possession date passed. The proposed possession date (Dec 2022) has passed with construction at 90.8%.
Satellite view of this address

Where it is · 184C pt/ CTS no. 231, Kurla

Area guide

What it's like to buy in Kurla

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Ghatkopar / VikhroliUpper-mid

Metro-1 anchor with Godrej's Vikhroli land bank next door.

Growth drivers:
Metro 1 interchange, Eastern Express Highway, corporate campuses.
Who buys here:
Families wanting east-side connectivity to BKC/Fort.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
Ladam Homes Pvt Ltd.

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P51800002692
Status
Ongoing
Stage
Certificate Signed
Possession
December 2022originally June 2021
Construction
90.8% complete
Units sold
0 of 0

Similar projects in Kurla

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Kurla compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.