High risk
  • Possession date passed. The proposed possession date (Dec 2025) has passed with construction at 77.7%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2025 per the RERA filing.
Satellite view of this address

Where it is · 285, 285/1 & 2, 285/4 TO 6 & 247(pt), Andheri West

Promoter

Builder profile

Builder
Gnanesh Virendra Lakhia

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
SAUMIL ASHWIN JHAVERI M/s H.M.Jhaveri & Sons. ASHWIN JHAVERI

Browse other projects associated with this architect to compare design and delivery patterns.

No other projects are linked to this architect yet.

Official RERA facts

Registration
P51800051955
Status
New
Stage
Certificate Signed
Possession
December 2025
Construction
77.7% complete
Units sold
17 of 41

Similar projects in Andheri West

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Andheri West compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.