Under construction
KESHAV VATIKA
MahaRERA P52100007032High risk
by UDAY INFRA
GAT NO. 98, MAVAL, 410506
Post your property hereOwn or renting out a unit in KESHAV VATIKA? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in MAVAL come to you.
Dec 2021
Possession
78.8%
Built
0
Complaints
0
Units
High risk
- Possession delayed ~3 yrs. Originally promised Mar 2019, now proposed Dec 2021 per the RERA filing.
- Possession date passed. The proposed possession date (Dec 2021) has passed with construction at 78.8%.
Satellite view of this address
Where it is · GAT NO. 98, MAVAL
Promoter
Builder profile
UDAY INFRA
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P52100007032
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2021originally March 2019
- Construction
- 78.8% complete
- Units sold
- 0 of 0
Similar projects in MAVAL
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
SHIVAY
MAVAL100% builtPoss. March 2019
ARIA
MAVAL100% builtPoss. March 2021
CHRISHH ARCH
MAVAL90.9% builtPoss. December 2018
SAPTAGIRI
MAVAL90.9% builtPoss. June 2022
VIHAR
MAVAL27.3% builtPoss. December 2021
RAGHUVANSHA APARTMENT 2
MAVAL0% builtPoss. March 2022
ABC NIVRITI
MAVAL0% builtPoss. October 2024
Keep exploring
Where this project sits, who built it, and how MAVAL compares.
In MAVAL
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 7 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.