KINGSBURY PHASE I
129P, 135/1, 138, 139, CHARHOLI, 412105
- Litigation pending (4). MahaRERA's litigation disclosure lists 4 pending cases against this project.
- Possession date passed. The proposed possession date (Dec 2022) has passed with construction at 96.8%.
- Promised amenities not started. Clubhouse is at 0% build with possession due Dec 2022 per the RERA filing.
Where it is · 129P, 135/1, 138, 139, CHARHOLI
Area guide
What it's like to buy in CHARHOLI
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52100001994
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2022
- Construction
- 96.8% complete
- Units sold
- 0 of 0
Similar projects in CHARHOLI
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how CHARHOLI compares.
In CHARHOLI
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.