High risk
  • Litigation pending (2). MahaRERA's litigation disclosure lists 2 pending cases against this project.
  • 1 appeal at MahaREAT. 1 complaint against this project has been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
  • Possession delayed ~2 yrs. Originally promised Mar 2024, now proposed Jun 2026 per the RERA filing.
  • Possession date passed. The proposed possession date (Jun 2026) has passed with construction at 96.5%.
Satellite view of this address

Where it is · 113/1 PLOT NO.2, Haveli

Area guide

What it's like to buy in Haveli

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
KALYAN JAGANNATH JADHAV

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
SATISH TAMASKAR

Browse other projects associated with this architect to compare design and delivery patterns.

No other projects are linked to this architect yet.

Official RERA facts

Registration
P52100008908
Status
Ongoing
Stage
Certificate Signed
Possession
June 2026originally March 2024
Construction
96.5% complete
Units sold
58 of 160

Similar projects in Haveli

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Haveli compares.

Data sourced from the official MahaRERA portal; complaints last synced 21 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.