High risk
  • Possession delayed ~2 yrs. Originally promised Apr 2025, now proposed Apr 2027 per the RERA filing.
  • Behind schedule. Possession is due Apr 2027 but construction is only at 9.5%.
Satellite view of this address

Where it is · 54/18A,18B, Thane

Promoter

Builder profile

Builder
KRISHNA ASSOCIATE

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P51700029686
Status
New
Stage
Certificate Signed
Possession
April 2027originally April 2025
Construction
9.5% complete
Units sold
0 of 0

Similar projects in Thane

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Thane compares.

Data sourced from the official MahaRERA portal; complaints last synced 24 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.