High risk
  • Possession delayed ~2 yrs. Originally promised Dec 2024, now proposed Apr 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Apr 2027 per the RERA filing.
Satellite view of this address

Where it is · 251/2/1, Mulshi

Promoter

Builder profile

Builder
Vastushilp Developers

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52100033444
Status
New
Stage
Certificate Signed
Possession
April 2027originally December 2024
Construction
57.3% complete
Units sold
0 of 0

Similar projects in Mulshi

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Mulshi compares.

Data sourced from the official MahaRERA portal; complaints last synced 24 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.