Post your property hereOwn or renting out a unit in KUBER MUDRA MEADOWS? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Ambegaon come to you.
Dec 2027
Possession
21.9%
Built
0
Complaints
0
Units
Caution
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2027 per the RERA filing.
Area guide
What it's like to buy in Ambegaon
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
KUBER MUDRA MEADOWS
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52100077821
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2027originally August 2027
- Construction
- 21.9% complete
- Units sold
- 0 of 0
Similar projects in Ambegaon
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Kokane Rich Heights
AmbegaonPoss. July 2027
CRYSTAL CROWN
AmbegaonPoss. July 2029
ANANDI MALHAR
AmbegaonPoss. April 2028
Aarambh Residency
AmbegaonPoss. April 2031
UPTOWN PLAZA
AmbegaonPoss. August 2030
Bella Casa - Phase 1
Ambegaon91.1% builtPoss. April 20271 complaint
VENKATESH LAKE LIFE PHASE 1
Ambegaon90.9% builtPoss. June 2018
ANURADDHA AT 168/27
Ambegaon90.9% builtPoss. December 2018
Keep exploring
Where this project sits, who built it, and how Ambegaon compares.
In Ambegaon
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 11 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.