High risk
  • Litigation pending (1). MahaRERA's litigation disclosure lists 1 pending case against this project.
  • Possession delayed ~3 yrs. Originally promised Dec 2024, now proposed Apr 2028 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Apr 2028 per the RERA filing.
Satellite view of this address

Where it is · SR NO.48/16A/21B 48/14B/1B, Haveli

Promoter

Builder profile

Builder
KUMAR ENTERPRISES

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
The Design

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P52100015579
Status
New
Stage
Certificate Signed
Possession
April 2028originally December 2024
Construction
52.7% complete
Units sold
25 of 116

Similar projects in Haveli

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Haveli compares.

Data sourced from the official MahaRERA portal; complaints last synced 17 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.