High risk
  • Possession delayed ~2 yrs. Originally promised May 2025, now proposed Jul 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jul 2027 per the RERA filing.
Satellite view of this address

Where it is · S N 75/7 and 76/4, Palghar

Promoter

Builder profile

Builder
JAY KHODIYAR CONSTRUCTION

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
GAURESH P NVALKAR

Browse other projects associated with this architect to compare design and delivery patterns.

No other projects are linked to this architect yet.

Official RERA facts

Registration
P99000048812
Status
New
Stage
Certificate Signed
Possession
July 2027originally May 2025
Construction
81.1% complete
Units sold
22 of 45

Similar projects in Palghar

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Palghar compares.

Data sourced from the official MahaRERA portal; complaints last synced 11 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.