High risk
  • Possession delayed ~2 yrs. Originally promised Dec 2023, now proposed Jun 2025 per the RERA filing.
  • Possession date passed. The proposed possession date (Jun 2025) has passed with construction at 67.3%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2025 per the RERA filing.
Satellite view of this address

Where it is · 192/3/C AND 192/4, Thane

Area guide

What it's like to buy in Thane

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
KYRAA INFRA PROJECTS PRIVATE LIMITED

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51700005769
Status
Ongoing
Stage
Certificate Signed
Possession
June 2025originally December 2023
Construction
67.3% complete
Units sold
38 of 64

Similar projects in Thane

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Thane compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.