Under construction

LATITUDE-STATUS REDEFINED

MahaRERA P51700032327High risk

by FLEXTON LIFESPACES PRIVATE LIMITED

PLOT NO - P-26/1 AND P-26/2 PATALGANGA INDUSTRIAL AREA, PATALGANGA, 410222

Official record
Apr 2027
Possession
41.8%
Built
0
Complaints
160
Units
High risk
  • Possession delayed ~1 yr. Originally promised Dec 2025, now proposed Apr 2027 per the RERA filing.
  • Behind schedule. Possession is due Apr 2027 but construction is only at 41.8%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Apr 2027 per the RERA filing.
Satellite view of this address

Where it is · PLOT NO - P-26/1 AND P-26/2 PATALGANGA INDUSTRIAL AREA, PATALGANGA

Area guide

What it's like to buy in PATALGANGA

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Navi Mumbai (Vashi–Nerul)Mid-income

Planned-city order — wide roads, node markets, established social infra.

Growth drivers:
Atal Setu (MTHL), metro lines, the upcoming Navi Mumbai airport.
Who buys here:
Professionals wanting planned-city living with airport-corridor upside.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
FLEXTON LIFESPACES PRIVATE LIMITED

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P51700032327
Status
New
Stage
Certificate Signed
Possession
April 2027originally December 2025
Construction
41.8% complete
Units sold
93 of 160

Keep exploring

Where this project sits, who built it, and how PATALGANGA compares.

Data sourced from the official MahaRERA portal; complaints last synced 17 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.