Under construction
Life Republic Sector R31/31st Avenue/24K-Espada
MahaRERA P52100051876High risk
by KOLTE-PATIL DEVELOPERS LIMITED
77/1P, 77/2P, 78/1P, 86P, Hinjewadi, 411057
Post your property hereOwn or renting out a unit in Life Republic Sector R31/31st Avenue/24K-Espada? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Hinjewadi come to you.
Dec 2026
Possession
29.4%
Built
2
Complaints
0
Units
High risk
- Behind schedule. Possession is due Dec 2026 but construction is only at 29.4%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Area guide
What it's like to buy in Hinjewadi
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
KOLTE-PATIL DEVELOPERS LIMITED
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52100051876
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026
- Construction
- 29.4% complete
- Units sold
- 0 of 0
Similar projects in Hinjewadi
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Life Republic - Sector R 17 B - 17 B Avenue - Nora
HinjewadiPoss. March 2022
Hinjewadi Project-Tower A
HinjewadiPoss. June 20311 complaint
Hinjewadi Project-Tower B
HinjewadiPoss. June 2031
Kohinoor Royale Towers
HinjewadiPoss. December 2030
Hinjewadi Premium - Tower 9
HinjewadiPoss. June 2031
Hinjewadi Premium - Tower 10
HinjewadiPoss. July 2032
Hinjewadi Phase 3 - Tower 15
HinjewadiPoss. December 2030
Hinjewadi Phase 3 - Tower 16
HinjewadiPoss. December 2030
Keep exploring
Where this project sits, who built it, and how Hinjewadi compares.
In Hinjewadi
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.