Under construction

LIFE VILLE

MahaRERA P52100003879High risk

by BHARAT SITARAM KATE

154 P, 155 1, 155 3, 156 1, 156 3, 158, 159, 156 2, 156 5, Pimpale Saudagar, 411027

Official record
Mar 2019
Possession
30.2%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Mar 2019) has passed with construction at 30.2%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Mar 2019 per the RERA filing.
Satellite view of this address

Where it is · 154 P, 155 1, 155 3, 156 1, 156 3, 158, 159, 156 2, 156 5, Pimpale Saudagar

Promoter

Builder profile

Builder
BHARAT SITARAM KATE

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100003879
Status
Ongoing
Stage
Certificate Signed
Possession
March 2019
Construction
30.2% complete
Units sold
0 of 0

Similar projects in Pimpale Saudagar

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Pimpale Saudagar compares.

Data sourced from the official MahaRERA portal; complaints last synced 5 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.