Lodha Majiwada - Tower 1
by MACROTECH DEVELOPERS LIMITED
28/5P, 29/6P, 29/7P, 29/8, 29/9P, 31/8P, 31/4P, 31/1P, 30/1P, 32/10P, Thane, 400601
- Litigation pending (2). MahaRERA's litigation disclosure lists 2 pending cases against this project.
- Possession date passed. The proposed possession date (Nov 2022) has passed with construction at 81.8%.
- Promised amenities not started. Clubhouse is at 0% build with possession due Nov 2022 per the RERA filing.
Where it is · 28/5P, 29/6P, 29/7P, 29/8, 29/9P, 31/8P, 31/4P, 31/1P, 30/1P, 32/10P, Thane
Area guide
What it's like to buy in Thane
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
A full city of its own — lakes, malls and township-scale supply along Ghodbunder Road.
- Growth drivers:
- Metro 4/5 corridors, big-brand townships, spillover from Mumbai pricing.
- Who buys here:
- Families upgrading to space and amenities without island-city prices.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51700013263
- Status
- New
- Stage
- Certificate Signed
- Possession
- November 2022
- Construction
- 81.8% complete
- Units sold
- 0 of 0
Similar projects in Thane
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Thane compares.
In Thane
The developer
Research