High risk
  • Litigation pending (3). MahaRERA's litigation disclosure lists 3 pending cases against this project.
  • Possession delayed ~2 yrs. Originally promised Dec 2024, now proposed Dec 2026 per the RERA filing.
  • Promised amenities not started. Clubhouse is at 0% build with possession due Dec 2026 per the RERA filing.
Satellite view of this address

Where it is · Survey No. 28/1, Haveli

Area guide

What it's like to buy in Haveli

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
KRISHNA CONSTRUCTIONS

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
Catalyser Design

Browse other projects associated with this architect to compare design and delivery patterns.

No other projects are linked to this architect yet.

Official RERA facts

Registration
P52100047958
Status
New
Stage
Certificate Signed
Possession
December 2026originally December 2024
Construction
90.9% complete
Units sold
8 of 16

Similar projects in Haveli

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Haveli compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.