High risk
  • Litigation pending (13). MahaRERA's litigation disclosure lists 13 pending cases against this project.
  • Behind schedule. Possession is due Sept 2027 but construction is only at 35.5%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Sept 2027 per the RERA filing.
Satellite view of this address

Where it is · 41A pt and 41B/1/1 pt, Andheri

Area guide

What it's like to buy in Andheri

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Andheri East / MarolMid-income

Office corridors (SEEPZ, MIDC) with value housing pockets between them.

Growth drivers:
Airport proximity, Metro 1/7, IT-park employment.
Who buys here:
Working couples prioritising commute over frills.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
Luma Tower C

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
Aakar Architects & Consultants

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P51800054472
Status
New
Stage
Certificate Signed
Possession
September 2027
Construction
35.5% complete
Units sold
87 of 173

Similar projects in Andheri

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Andheri compares.

Data sourced from the official MahaRERA portal; complaints last synced 24 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.