🏗️
Under construction

Magic Meera Heights

MahaRERA P51700049394High risk

by Magic Star Developers

S.No 141/2(Old)12/2(New), Mira, 401107

Official record
Dec 2026
Possession
50.9%
Built
0
Complaints
152
Units
High risk
  • Possession delayed ~1 yr. Originally promised Dec 2025, now proposed Dec 2026 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Satellite view of this address

Where it is · S.No 141/2(Old)12/2(New), Mira

Area guide

What it's like to buy in Mira

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Dahisar / Mira RoadValue

The city's northern value frontier, densifying fast.

Growth drivers:
Metro 9 extension, spillover from Borivali pricing.
Who buys here:
First-time buyers stretching for a 1–2 BHK.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
Magic Star Developers

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
Dinesh N Patel n Patil

Browse other projects associated with this architect to compare design and delivery patterns.

No other projects are linked to this architect yet.

Official RERA facts

Registration
P51700049394
Status
New
Stage
Certificate Signed
Possession
December 2026originally December 2025
Construction
50.9% complete
Units sold
84 of 152

Similar projects in Mira

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Mira compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.