Caution
  • Possession date passed. The proposed possession date (May 2022) has passed with construction at 90.9%.

Promoter

Builder profile

Builder
PRABHAV VIJAY KHAWASE

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P50500024213
Status
New
Stage
Certificate Signed
Possession
May 2022
Construction
90.9% complete
Units sold
0 of 0

Similar projects in DIGHORI

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how DIGHORI compares.

Data sourced from the official MahaRERA portal; complaints last synced 21 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.