- 1 appeal at MahaREAT. 1 complaint against this project has been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
- Possession date passed. The proposed possession date (Dec 2022) has passed with construction at 81.8%.
Where it is · 158, 183 P ,183 P Plot No 1, nandore
Area guide
What it's like to buy in nandore
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P99000015852
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2022
- Construction
- 81.8% complete
- Units sold
- 0 of 0
Keep exploring
Where this project sits, who built it, and how nandore compares.
In nandore
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.