High risk
  • Possession delayed ~4 yrs. Originally promised Dec 2018, now proposed Jun 2023 per the RERA filing.
  • Possession date passed. The proposed possession date (Jun 2023) has passed with construction at 81.8%.
Satellite view of this address

Where it is · SURVEY NO 241, Nashik (M Corp.)

Promoter

Builder profile

Builder
SATISH MANOHAR DESHPANDE

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P51600003147
Status
Ongoing
Stage
Certificate Signed
Possession
June 2023originally December 2018
Construction
81.8% complete
Units sold
0 of 0

Similar projects in Nashik (M Corp.)

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Nashik (M Corp.) compares.

Data sourced from the official MahaRERA portal; complaints last synced 12 Sept 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.